The NLCRPD is providing the following advisory issued by the Warwick Township Department of Public Works for roadway improvement projects scheduled to be completed this week. These schedules are dependent upon appropriate weather conditions. Please see the following adjusted paving schedule. This schedule may change again depending on the weather. During paving Township employees will be on site to help with traffic at all times.
Day #1 - Thursday August 26th
Application of paving fabric on Anita Drive, Sylvia Drive, Windy Hill Drive, and East Windy Hill Drive. Once the fabric is applied it is able to be driven on, but residents should still use caution when turning. These streets will also receive a leveling course of pavement on top of the fabric that again can be driven on after it has been rolled.
Day #2 – Friday August 27th
The final wearing course will be applied to Anita Drive, Sylvia Drive, Windy Hill Drive and East Windy Hill Drive. A leveling course and the final wearing course will also be applied to Rabbit Hill from SR 772 to Church Road.
Day #3 – Monday August 30th
Milling and paving will take place on Owl Hill Rd from SR 501 to the paving joint about 100 feet East of Shober Lane. Local businesses will have access during the paving and Township employees will be on site at all times to help with traffic.
The following detours will be in place.
-Landis Valley Rd to East Woods Drive to Kissel Hill Rd to Millport Rd to SR 501
-Cedar Street to East 6th Street to SR 501