The following road work is scheduled to take place (weather permitting) from June 7th- June 11th .
Disstonview Drive - Storm water improvements and some minor asphalt repair will be taking place on dead end portion of Disstonview Drive on June 7th. During this work emergency vehicles, residents and deliveries will have access.
Rabbit Hill Rd - Asphalt repairs will be taking place on portions of Rabbit Hill Rd from June8th thru June11th. Portions of the road will need to be closed for this work and a short detour will be in place. Emergency vehicles, deliveries , and residents will still have access and township employees will be on site to help vehicles through the work areas if needed.